JXMX18 输电线路工程监理工作总结
输电线路工程
监 理 工 作 总 结
(监理公司名称)
(加盖监理公司公章)
年月
批准:(分管领导)
审核:(公司职能部门)
编写:(总监理工程师)年月日年月日年月日
目 次
1 工程概况 ···································································································································· 106 2 监理组织机构、监理人员和投入的监理设施 ················································································ 106 3 监理合同履行情况 ······················································································································ 106 4 施工过程中发现问题的处理方式 ································································································· 106 5 监理工作成效 ····························································································································· 106 6 工程大事记 ································································································································· 106 7 监理工作体会 ····························································································································· 106
1 工程概况
【编写说明】描述工程整体概况和本施工监理标段的具体工程情况。
2 监理组织机构、监理人员和投入的监理设施
【编写说明】描述监理项目部的组织机构情况,监理人员投入情况,监理办公设施、检查检测器具投入情况。
3 监理合同履行情况
【编写说明】监理合同履行情况需着重说明在“四控制、二管理、一协调”工作中如何采取有效控制,采取何种措施和技术方案,取得什么样成绩,要有一定的数字说明和依据资料。具体编写下列内容:
(1)策划阶段监理工作情况:描述监理项目部在工程策划阶段的工作情况,包括监理策划文件的编制;对施工项目部主要施工策划文件的审查及对工程开工条件核查等的监理工作情况。
(2)质量控制情况:要体现督促承包单位建立和完善自身质量体系,重点描述质量预控、自检、试验检查和旁站等情况,以及质量控制成果。
(3)安全文明控制情况:要体现文件审查、日常安全文明检查、签证、旁站等工作内容及安全文明控制等情况。
(4)进度控制情况:如何依据合同和业主要求,加强并细化进度计划中监督管理,重视施工进度的记录、信息收集、统计、分析预测和报告工作,从而达到监理进度控制工作成效等情况。
(5)造价控制情况:要详细说明做好工程计量与支付的审核签证工作,如何进行合同变更、设计变更等审核控制。在合同工程总量控制的前提下,如何加强分析预测、提高审核工作准确性、可靠性和原则性,实现投资效益,累计为业主节约资金程度的情况等。
(6)合同管理情况:重点说明熟悉、执行合同的情况,公正处理合同争议;对设备供货单位合同履约情况的检查和评价;配合建设单位实施对设计单位、施工单位资信及综合评价的工作情况。
(7)信息管理与组织协调:重点说明监理项目部信息资料管理的情况;通过工地例会等方式及时开展工程组织协调,处理各种关系,协调好业主、设计和承包单位各方关系的情况。
(8)技术管理情况:重点说明监理项目部在技术管理上所做的工作,包括对重大技术方案的审查、对工程技术标准提出的合理化建议、工程变更的执行检查情况、工程“四新”应用情况等。
4 施工过程中发现问题的处理方式
【编写说明】描述施工过程中发现问题闭环管理的方法。
5 监理工作成效
【编写说明】描述监理工作绩效及工程目标的实现情况,监理过程中取得哪些成绩,给该工程带来了哪些成效及监理项目部的创新等。
6 工程大事记
【编写说明】对工程主要重要事件的描述。
7 监理工作体会
【编写说明】通过该工程监理得到了哪些提高,如何做好今后的监理工作。
◈ 输电线路个人工作总结 ◈
我局在县委、县的领导下,在市电力局的指导、支持下,坚持“安全第一,预防为主”的方针,以“安全责任、重点突出、标本兼治、整章建制、重在治本”为工作重点,以“安全发展、科学发展”为主题,按照安全标准化建设的要求,以“一岗双责”为重点,进一步加强了安全管理工作,全面推进安全生产各项工作,为实现安全生产、保障群众生命财产安全作出了应有的贡献。现将我局开展安全生产管理情况汇报如下:
一、加强领导,落实工作责任
我局对安全生产工作高度重视,成立了以局长为组长,分管副局长为副组长的安全生产领导小组,并下设立专门工作小组,明确专人落实安全生产管理的各项工作任务,制定了切实可行的安全生产管理工作制绩考评细则,建立健全了各项规章制度,使安全生产管理工作有章可循、有制度可依。
二、健立健全安全生产管理制度
根据安全规章制度的规定,结合我局的实际情况,我局制定出台了《安全管理制度》,并于xx月xx日下发了《关于开展xx年度安全生产百日督查工作的通知》,对我局安全管理工作做出了规定的要求。各科室负责人、各单位负责人为安全生产工作第一责任人。
三、加大宣传力度,提高安全意识
为了提高全局人员对安全生产工作重要性的认识,局领导亲自带队,在全局范围内,开展了一系列安全活动:一是组织全局职工,在局办公室门前和会议室悬挂安全横幅;二是在办公室和各楼层办公室张贴安全生产宣传标语,向全局职工、各级安全管理人员、全局职工和家属发出安全生产宣传资料1000余份;三是在局电视台、电子屏幕上播放安全生产专题片20多次。
四、强化检查、及时整改、落实整改
我局结合安全生产管理工作实际,按照“全面排查、突出重点、防范风险”的要求,以“安全生产月”、“安全生产百日督查”活动为契机,进一步强化对安全生产工作的领导,建立健全安全生产管理体系,加强对安全生产各项规章制度的宣贯和贯彻落实,严格执行“两票三制”、“三级安全管理”等规章制度,落实好安全隐患排查治理责任制,坚持每半月对全局生产系统安全生产、消防安全、交通安全、用电安全、电力安全、用气安全等工作进行一次大检查,发现隐患立即处理。
◈ 输电线路个人工作总结 ◈
此次新入企员工专业与岗位培训,我参加的是配电线路运行与检修作业员岗位培训,配电班的培训内容分为理论课程和实际操作两大部分。作为学员,我认为这样的课程安排是很科学,很合理的。理论和实操先后进行,以理论作为指导,实操作为深化,使培训变得更加系统,更加有实际价值。
配电班的理论部分共安排了十一门课程,课程内容涵盖了配电系统的方方面面。授课老师也是从贵州电网公司各个分公司抽调过来的资深专家,老师结合实际与自己多年工作经验的授课方式,给与我们很多启迪,使我们受益匪浅。我们不但学到了理论与原理,而且学到了实际中这些理论与原理的用处,在潜意识中将理论与实际有机地结合在一起,使记忆更加深刻,以前遇到的.一些问题也得到了解决,理论课程的学习补充丰富了我们的配电系统知识框架。
我们配电班实操部分的内容是最多的,而且可以说是最需要体力的。作为配电班唯一的女生,实操对于我来说是一个很大的挑战。感触颇深的就是登杆训练了,由于我的脚比较小,找不到适合我的脚扣,脚扣总是从脚上滑落下来,脚趾翘起来可以勉强挂住脚扣,但是这样脚扣又挂不到电杆上,总是踩空,而且脚扣比较重,腿带起来很吃力,有时候就直接挂到杆子上带不起来。为了帮助我完成训练内容,我们余老师就用手帮我抬着脚扣,一步一步的鼓励我向上爬,在如火的骄阳下,我看到老师额头泌出细细的汗珠,我暗暗下决心一定要把登杆练好。
经过了一天的练习,我已经可以熟练地上下电杆了,但是一直没有登上杆顶,老师又鼓励我继续前进,要爬上杆顶,做一个合格的线路工人。为了消除我的心理顾忌,老师给我做了充分的安全措施,在培训老师和配电班同学的鼓励和期待中,我向杆顶登去。登上杆顶的那一刻,我的心忽然不紧张了,取而代之的是一片坦然。感觉自己一下子长大了,不再畏惧,不再害怕,我已经成功战胜了自己,超越了自己。在接下来的培训中,我又完成了横担的安装和拆卸,虽然有困难,完成的过程也很坎坷,但我并不想放弃这样难得的机会,我感觉自己在培训的每一天都在成长,我要好好珍惜,争取每一次可以利用的机会,取得更大的进步。
通过这次培训,我不仅丰富了自己的理论知识,对配电系统的认识更加系统,而且锻炼了自己的实际动手能力,可以说经过这次培训,我们至少缩短了半年的成长期。此外,对我自己来说,最大的收获就是我现在敢于挑战我自己,敢于和昨天的自己说不,面对问题和困难时,我可以更加冷静,更加自信。在接下来的培训中,我会更加努力,争取更大的进步,为今后更好的工作做好准备。
◈ 输电线路个人工作总结 ◈
xxx 男 汉族 1974年12月出生 学历中专 1991年布尔津供电有限责任公司参加工作从事配电线路工作 20xx年在乌鲁木齐电力培训中心参加配电线路培训取得配电线路技师资格证书。
本人从事配电线路运行、检修、故障抢修专业十年有余,之前是送电线路检修专业干了十四年,两个专业之间有相近之处,但也有很多的不同,配电运行专业增加了变压器、开关、刀闸、避雷器、无功补偿电容器等很多电气设备,而送电线路专业则接触不到。要想把这些设备管理好并且安全可靠的运行,就必须熟练掌握相应的专业知识和技能,所以,我是一边工作、一边学习、实践,又借助高级工、技师培训的机会,来不断充实自己的配电运行专业知识,经过几年的刻苦学习和实践,现在工作起来还算是得心应手。
一、提高学习的自觉性,增强自身专业技术素质。
几年来,本人一直利用书本、向老师傅、并通过专业培训等努力学习配电专业知识,学习新设备的管理、运行和配电设备新技术。由于配电设备的日益更新,新产品、新技术层出不穷,只有不断的学习,掌握更多的新知识、新技术,才能掌握和管理好配电网络新设备。通过学习和实践,目前本人对新型变压器、10v柱上开关、10kv电缆分支箱、环网柜等有了一套比较成熟的管理和运行经验。对供电事故的分析和判断相对比较果断、准确,有效地减少了事故处理的时间,无论是公司领导或客户都能给予充分的肯定。
二、加强配网的设备管理
◈ 输电线路个人工作总结 ◈
转眼间,进入供电公司实习的第一站——配电中心的实习即将结束。短短的三周时间,让自己对电力系统、对工作都有了一个初步的了解,也让我懂得了一些隐藏的知识。从学校到社会的大环境的变化,身边接触的人也完全换了角色,老师变成了老板,同学变成了同事,相处之道也完全变得不同了,虽然之前有过这方面的心里准备,但是真正地融入到这巨大的转变当中,还是有点不适应,彷徨过、迷茫过,无法马上适应新的环境。但,好在大家都是刚刚从学校出来,有问题大家都可以互相帮忙。
第一天,负责我们这组实习的刘阿姨就为我们每人印发了《20xx年新入职员工现场培训手册》,让我们了解到荆州供电公司配电中心的主要职责是担负荆州城区范围内配电设施的运行与维护、配网的规划、设计与施工,参与客户报装工程的方案制定、设计审查、工程验收工作以及负责城区配网技术线损的计算与管理。同时也让我们了解此次实习的主要内容有两大块。一个是进行安全教育及安规考试,学习电力相关法律法规及规章制度;另一个是维护抢修站跟班实习,要熟悉运行维护及抢修的工作流程、配电线路及其设备现场运行规程、运行值班的职责和记录登记、了解各类工器具的使用方法、设备道闸操作及现场标准化作业的管理流程。同时一再强调进入电力生产现场实习时遵循“多看、多听、多问、多思考、不动手“的原则,在从事电气工作前,要做到“四清楚”:作业任务清楚,危险点清楚,作业程序清楚,安全措施清楚。在作业工程中“三不伤害”:不伤害自己,不伤害他人,不被他人伤害。
跟着一周的时间我们都在学习《电力安全工作规程》,由于刚开始参加工作,实际工作经验严重匮乏,制约了我们对安全生产认识的提高,很多时候看安规条例,对里面的规定只知其然而不知其所以然,没有实际接触操作过,很多东西从字面都难以理解,因此只能死记硬背。后来安保科的陈阿姨来为我们梳理了一下在配电工作中需要用到的安规条例,在讲得过程中穿插讲了一些实例,理解起来就容易多了,并且简单的跟我们讲了下紧急救护的知识。然后还介绍了安规考试的一些要求,提醒我们不再是学生时代的六十分为及格线,而是八十五分,有些时候甚至要求是百分百。通过学习,知道了很多事故发生的主要原因是作业人员未认真执行安全操作规程,不按章作业,工作责任人现场查勘不到位。在以后的实习过程中,我要严格遵守在施工现场穿工作服、戴安全帽的规定,把“安全第一,预防为主”的思想落实到日常工作的每一个小细节中去。我想,这也是我在以后的工作中要充分注意的。
随后的一周我们被分成三个小组,分别到荆州维护站、沙市维护站和开发区维护站进行跟班实习,而我则被分在了沙市维护站。到达维护站后,鲍站长简单的问了下我们之前的学习情况,问我们学习安规没有,学了多久等等,我们如实回答,本以为会安排人带我们去现场看看。结果,鲍站长说继续学习一个星期安规,我们一脸疑惑得看着他,因为我们刚学了一周的安规。估计鲍站长是看出我们的疑惑了,就问我们还记不记得“三级”教育,即公司教育、车间教育、班组教育,还告诉我们要想到现场,就要进行最后一级教育——班组教育,并考试合格才能放心让我们去现场看。虽然心里一直感觉没那个必要,但是一想到曾经发生的那些惨不忍睹的安全事故,不说为了公司起码为了自己的安全,多学点记熟点也不是坏事。于是我们又开始了一周枯燥的安规学习。
在维护站的两周里每天看着工人师傅们早出晚归的为保障老百姓的安全用电而忙碌,心里的敬意油然而生,想到自己能幸运的成为电力人而自豪。实习期间不仅是我积累工作经验的重要阶段,也是我努力学习的宝贵时间。“三人行,必有我师”。维护站的每一位都是我的老师,他们丰富的工作经验对我来说是一笔宝贵的财富。虽然最后因为种种原因没能去现场有点遗憾,但却牢记了保证安全的组织措施和技术措施,进一步的熟悉了安规条例,为以后的学习、工作打下了坚实的基础。
配电公司党员总结
开展创先争优活动,是党中央创新和加强基层党组织的一项重大举措。我按规定认真学习了有关创优争先方针政策,以及有关领导的讲话,思想认识有了很大的提高,深深认识到开展先进性教育活动的必要性和重要性,增强了努力搞好工作的责任感和使命感。
现将我在省电力公司一班“创优争先”活动中的所作所感、思想根源和今后的努力方向总结如下:
一、所作所感
1、刻苦学习配电系统各项知识技能。我深知在工作中,对社会主义初级阶段理论、市场经济理论、"三个代表"重要思想的学习没的提到应有的高度。特别是理论的学习还不够系统,学习还浮在表面,还没有达到应有的深度。有时只顾忙于一些具体的工作,自觉主动在挤时间学习不够,闲时学一阵子,忙时学的少,有时看报纸也是看看大标题,结果对理论上的一些问题,尤其是一些新问题理解还不深。
2、政治理论方面的内容看得多,市场经济理论,法律知识,电脑知识,科学文化知识等钻研得少,结果使得知识面不够广。在思想上对国家电网工作人员应具备全面的素质,掌握更多知识的重要性认识不足,认为自己是从事机关工作的,只要有一定的政治理论功底就行,其他方面的知识多少知道点就可以过得去。
3、开展批评与自我批评做得不够。在会上作自我批评多,在其他情况下作自我批评少;批评别人打不开情面,不够大胆,怕伤害同志间感情,不利于工作的顺利开展。认为目前整个大气候也就如此,认真开展批评与自我批评也不一定就解决问题。
4、为人处世有时不够恰当,不够策略,特别是对同志的批评和对同事的指导及批评,有时不够讲究方法,结果使同志们有时候出现比较勉强的现象。对工作方法,处事艺术的重要性认识不够,总认为自己的指导思想是好的,方法问题欠缺一些,同志们都会相互谅解的。
5、协调能力不强,与部分群众沟通少,有时工作不细致。这一点与我的性格有很大关系,我是一个不善交际的人,也没有往这方面做过努力。而现代的社会,除了需要真才实学外,还需要学会与人沟通,努力推销自我。在平时工作中,我只管工作,而不管与人交流,不生动活泼,特别是与领导及部分同志的沟通少了,与社会的溶合度也不够,认为只要工作做好,就万事大吉了,这样造成有时工作不细致。
二、活动参加情况:
随着配电一班党支部和班级的思想政治建设,本班开展了一系列以创优争先为主题的活动
在思想方面,我们班级党支部的博客在十一月初成功开设,每位党员在活动期间以网络博客为载体,定期把活动期间的照片和活动细节都发表在博客上,各位党员或者团员都在博客上讨论活动开展的效果和个人感受,这项活动让我感受到了一阵温暖。
在心理方面,我们经常组织以学习小组为单位,开展时事讨论学习,由组长负责在博客上发表,开放评论,帮助广大党员和班级同学解决培训期间的心理问题。
在体魄方面,我经常参加我们党支部和班委会共同号召全班学员开展一些体能训练,比如组织大家打篮球,打羽毛球,跑步等等活动,身体是革命的本钱。
在技能方面,我参加了我们班级内部成立专业技能互助小组,形成“一帮一”学习模式,发挥优秀技能学员以点带面的作用。
此外我们班党支部每月定期开一次专题会议,大家可通过博客发表个人意见,及时发现问题,及时研究解决,使创先争优活动扎实有效的开展。
三、努力方向:
我要立足于工作进步和自身全面发展,广泛学习一切有益知识。加强对经济、政治、文化、科技、法律、管理、历史等基本知识的学习,加强对履行当前岗位职责所必需的专门知识和技能的学习,并把这些方面的学习同深刻领会和灵活运用“创优争先”四个字紧密结合起来。既学习与自己的电力行业专业技能知识,也要广泛涉猎多方面的知识,多学习一些反映当今世界文明进步的新知识、新经验,做到"专"与"博"相结合,求知与修身共进步,使知识结构更加合理,个人素质全面提高。
◈ 输电线路个人工作总结 ◈
一、 前言
实习对于我们这些一直待在课堂上上课的大学生来说,无疑是能够加深我们对理论知识的理解。而且对于即将毕业的我们来说,实习是个很好的职业探索期,我们可以通过实习工作的锻炼,开始了解职场,了解自己本专业的职责、工作内容等,这就提供了一个很好的机会,在此过程中探索个人职业目标和职业定位,即未来的发展方向和个人的定位。
这次实习的主要任务有用经纬仪进行分坑测量,如何使用绳子对伤者和各类工具进行绑绳结练习,使用两个脚踏板脚扣进行登杆练习、攀登铁塔练习、更换铁塔线路上的防震锤。这些练习使我们对电工技术有了一定的认知,对电工技术等方面的专业知识有了进一步的理解。同时通过实习熟悉登杆塔和杆塔上作业的一般操作规程,了解登杆塔和杆塔上作业的安全知识,掌握用输电线路现场工作的基本方法和技能。
当然,这样的实习也能使自己对自己对自己本专业将来是用来做什么的,它的应用领域有哪些,以及自己将来的工作环境是怎么样的也有一个清楚的认识。
二、 实习内容
1、实习时间
2014年11月24日至2014年12月2日
2、实习使用的设施、器材和工具
安全帽、手套、安全带、扳手、踏板、经纬仪、脚架、标尺、绳子、木棍、绝缘子、绝缘子串、皮尺
3实习项目及操作要就
用踏板登水泥杆练习、攀登铁塔练习、更换铁塔线路上的防震锤、用经纬仪进行分坑测量和用绳子对伤者和各类工具进行打绳结练习。
(1)、如何穿戴安全帽、安全带等安全护具
a、佩戴安全帽的作用及要求:安全帽是重要的头部保护用品,在劳动作业过程中有异物撞击头部时能起到有效的缓冲和保护作用。安全帽在佩戴前,应调整好松紧大小,以帽子不能在头部自由活动,自身未感觉不适为宜。 安全帽由帽衬和帽壳两部分组成,帽衬必须与帽壳连接良好,同时帽衬与帽壳不能紧贴,应有一定间隙,该间隙一般为2-4cm,当有物体坠落到安全帽壳上时,帽衬可起到缓冲作用,不使颈椎受到伤害。必须栓紧下颚带,当登高作业或身体倾斜时,不至于脱落。
b、系安全带的作用及要求:防止登高作业时意外落地,保护作业人员在登高作业时不从高空滑落。有可能进行高空作业的工作,在进入工作场所时,身上必须佩有安全带;高度超过2米的高空作业,必须配有安全带; 系安全带时要束紧腰带,腰扣组件必须系紧系正;利用安全带进行悬挂作业时,不能将挂勾直接勾在安全带绳上,应勾在安全带绳的挂环上;登高作业时,禁止将安全带挂在不牢固或带尖锐角的构件上;安全带的各部件不能擅自更换;受到严重冲击的安全带,即使外型未变也不可使用;严禁使用安全带来传递重物且安全带要挂在上方牢固可靠处。
(2)、经纬仪进行分坑测量
在进行经纬仪实地测量前,何老师就借用在课堂上的时间给我们先讲了如何使用经纬仪及其操作要领和注意事项,当然也教给了我们如何使用经纬仪进行分坑测量。虽然课堂上同学们都非常认真的听老师讲,但是当我们到达现场,真正操作经纬仪的时候就发现了很多问题自己还没法解决。首先第一步要做的是将经纬仪对中整平,对中的目的是使仪器的中心和地面点在一条铅垂线上。整平则需要分两步进行,第一步是初步整平:调整三角架高度,使圆水准气泡居中。第二步是精确整平:调整三只脚螺旋,使管水准气泡居中。
整平时,首先转动照准部,使照准部水准管平行于一对脚螺旋,转动这两个脚螺旋,使气泡居中,然后,将照准部旋转90度,转动第三个脚螺旋,使水准管气泡居中,整平要反复进行,直到照准部转到任何位置时,气泡都居中为止。经纬仪摆好后,通过望眼镜应调节目镜使十字丝成像清晰,转动调焦螺旋使物像清晰。然后利用皮尺以及已给出的方向定出第一个点,接着将经纬仪盘右90度,用皮尺在这个方向上定出另一个点,将两点连线,再根据l1=√2/2(x-a)=0.707(x+a),l2=√2/2(x+a)=0.707(x+a),l0=√2/2x=0.707x算出直线正方形铁塔基础的分坑尺寸。以此类推分别测量出其他三个铁塔基础的分坑位置。
(3)、用绳子对伤者和各类工具进行打绳结
绳子对于现场的工作人员来说是非常重要的,因为绳子的作用非常的多。所以如何使用好绳子也是我们这次实习中非常重要的一部分。这一部分也是何老师教的,何老师说打绳结的要点是要绑的简单可靠牢固,拆还有方便,所以我们这次学习打的绳结叫做正反8字结。这种打法主要用来绑工具的,例如安全帽、扳手、棍类、绝缘子等等。当然绳子在紧急时刻也是能发挥很多的用处的,比如用它来绑住在杆塔上出现意外的工作人员,这种绳结和8字结有所不同,当然这种绳结也是非常可靠和容易绑。现场我们在老师的示范下纷纷练习起来。这一部分对我们来说还没太大难度的。
(4)、踏板登水泥杆
登杆是杆上作业必须要学会的一个技能,常用的登杆工具有:铁脚扣、带胶皮的铁脚扣、踏板、蹬杆携带的工具、安全带等。这次我们使用的工具是两块踏板。爬杆前我们应该正确戴好安全帽,扣紧帽扣,检查并扎好安全带,将安全带系在后背上部位置。需要监护的工作,监护人到位。然后检查踏板是否损坏,绳子是否有断股,检查安全后将踏板绑在水泥杆上,然后用脚踩上踏板进行冲压实验,确保安全后进行登杆。先将踏板绑在高过人头顶20公分的位置然后左手握着踏板,右脚登上踏板,左脚翘住绳子登上踏板,站稳后绑第二块踏板,同样左手握踏板,右脚登上踏板同时左脚绕过绳子踩在水泥杆上右手拉紧第二块踏板的绳子,左手将第一块踏板拆下然后左脚再翘绳站上踏板。就这样一步一步往上登,爬上去后需要将腰上的安全绳系在水泥杆上,然后进行杆上作业。下来时相对上去容易一点,将上面的踏板绑在下面然后爬下来,同样需要翘脚站稳再拆上面的踏板。就这样一步一步的爬下来。这一部分对于平时没怎么运动的`大学生来说无疑非常大的挑战。很多同学在踏板上很难保持平衡,以至于最后失去平衡后掉下来,当然这次实习做足了安全措施,背后面的安全绳就起到至关重要的作用,确保学生不会掉下来,但是磕磕碰碰是在所难免的了。
(3)、攀登铁塔
在攀登铁塔练习的需要使用防坠器,它是利用速差原理制做而成的,即突然加速的时候,防坠器就会在限定距离内快速制动锁定,保护人体安全。攀登铁塔用的防坠器,它是有方向性的,即在攀登的时候它可以跟随的你一同上去,但在下的时候,需要把防坠器放在腰的上面一点,用腰部的力使防坠器受一个水平的拉力,保持均匀的速度下塔,这样的话,防坠器就会跟随你一同下去,但是如果你的速度突然加快,防坠器就会制动,如果是失足的话就可以起保护作用。当防坠器制动后,应用手去轻轻的推它。在铁塔上水平移动工作面时,必须系好二道保护;要有足够强度的安全带,并应将绳子牢系在坚固的建筑结构件上或金属结构架上,不准系在活动物件上。在攀登铁塔的时候应该胆大心细,手抓稳,脚踩稳,不慌不乱,不急于求速度。在下杆的时候,保持均匀的速度带动防坠器一起下,同时也要注意安全,不贪快。师傅解析完防坠器的使用方法和注意事项之后,就带我们到铁塔那让我们练习攀登铁塔,这次师傅没给我们演示,可能在他们看来铁塔比电杆要安全很多,所以我们穿戴好安全护具后便开始了攀登练习,铁塔有18米,第一次爬到顶,很多同学都有点发怵,有的同学在爬的过程中脚也是抖的厉害。最后,我们也都是完成了这部分的任务。
(5)、更换防震锤
防震锤加挂在线路塔杆悬点处,以吸收或减弱振动能量,改变线路摇摆频率,防止线路的振动或舞动。用于消除线路自振以及消除风等引起的谐振。防震锤的安装距离的起点为悬垂或耐张线夹出口上标到防震锤夹板的几何中心。由于之前有很多组都在我们之前做过了更换防震锤的更换,所以这次师傅没有进行演示我们就开始自行练习了。这次更换防震锤我们是需要爬上铁塔然后再爬到线路上坐在上面仅靠自身的调整来维持自己平衡。在保持自己的平衡的同时我们还需要将防震锤拆下来然后再装回去。这对于平衡力不行且第一次练习的我们来说是非常困难的。很多同学更换完下来全身都是汗,个别同学稍不留神便从线上掉下来,幸好安全绳把他吊住了。这一部分是我们这一组实习的最后一部分,也是比较困难的一部分。
三、实习收获和感受
为期两个星期的输电线路技术实习让我对自己所学的专业有了更深层次的了解。通过这次的实习和与何老师的交流,发现自己知识的匮乏还有很多是自己不懂和没学到的。这让我我懂得了学习的重要性,了解到理论知识与实践相结合的重要意义,学会了坚持、耐心和努力,这将为自己今后的学习和工作做出了最好的榜样。我觉得作为电气工程及其自动化(输电线路工程方向)专业的学生,这次输电线路技术实习是非常有意义的。使我们对输电线路技术等方面的专业知识作进一步的理解,是我们对以后的工作有了一定的感性和理性认知。不仅培养和锻炼了我们的实际动手能力,更是使我们能够亲身接触到输电线路现场的实践工作情况,几天的实习下来感觉投身输电线路这方向必须要有强健的体魄,虽然实习只有短短的一个星期,虽然每天爬杆攀登铁塔只有一两次,但是每次上去下来都已经疲惫不堪。登杆作业最主要的两点莫过于体力充沛,胆大心细。这也让我暗暗下决心,接下来要好好锻炼好自己的身体。
这次带队培训的何老师说,我们的实习时间只有两个星期,这个时间对于整个正规培训来说是非常短的,因此我们并不能很深入的去真正熟悉输电线路一些相关的东西,但是对于这次实习我们的热情都比较高,在完成自己的实习任务的同时也积极的向老师提出自己不懂的问题,所以受益颇多。
四、对本次实习课程的意见、改进措施及建议
这次的实习老师们安排的挺好的,对我们的人身安全考虑的比较全面。在时间安排上一比较合理,因为都是体力活,所以没有高负荷的进行练习。给我们有较为充足的休息时间。至于建议,我个人是觉得实习如果能安排在大一会比较好一点,这样可以让我们从一开始就能对自己所学专业有一个较为全面的认识,可以安排在大一的专业认知这么课上。
五、结束语
时间匆匆,大学也来到的了最后一年,这次实习的结束,大四的课程安排也接近了尾声,自己的学生生涯也将要结束了。现在已经半只脚踏出了社会,也面临着毕业和就业的问题了,略微还是有点伤感和迷茫的,但是我们都应该要以积极的心态去面对。很感谢大学期间老师们对我的栽培和教导。
◈ 输电线路个人工作总结 ◈
电缆分支箱、环网柜等有了一套比较成熟的管理和运行经验。对供电事故的分析和判断相对比较果断、准确,有效地减少了事故处理的时间,无论是公司领导或客户都能给予充分的肯定。
一、加强配网的设备管理
第一,针对沛城区配电线路陈旧、设备老化、故障常出的现象,积极工作、大胆探索、实践,制定了一系列的改造方案:
(1)改造公用变压器接线桩的接线方式:由于公用变压器的性质所决定,负荷变化无常,变压器接线柱及螺栓式设备线夹受温度变化影响大,常造成设备线夹与导线连接松动,且设备线夹与变压器接线柱的接触面积也达不到运行规程要求,故经常出现故障。针对这种情况,就将所有公用变压器的出现导线采用液压式压接鼻,消除了设备线夹受温度影响大的缺陷,接线柱上采用了握手线夹,增大了接线柱的接触面积,有效的避免了变压器接线桩故障的发生。
(2)经测试,城区公用变压器的的工作接地和保护接地桩因年久锈蚀,接地电阻值很多不符合规程要求,2001年将城区90余台变压器的接地桩进行了更换,为设备的健康运行提供了保障。
(3)在三年的城网改造中,根据沛城区供用电特点,初期由本人为生技科提供了一套沛城区配电供电网络设想图,为城网改造的合理性、经济性提供了依据。其次是严把工程质量验收关,根据验收技术规程要求,对城网改造、业扩增容、用户工程等的中间及终结验收严格把关,确保新设备在接入电网运行前的施工质量全优。为新设备安全、可靠的运行奠定了基础。
第二,认真做好所属设备的巡视和消缺工作,结合配电设备早、晚峰负荷测量和电压测量,及时调整公变容量,使公变在额定输出电流的80%左右运行,20xx、20xx年沛城区没有发生一起因过负荷而烧坏公变的'事故,同时结合一年中夏冬季节的高峰用电期,制定迎峰渡夏和迎峰渡冬的相应措施,增加夜巡和特巡次数,发现异常情况,及时处理,确保供电设备安全可靠运行。
第三,积极组织开展各季安全大检查,结合安全性评价工作,对所辖配电线路及设备认真巡视消缺,做到了充油设备无渗漏、一类设备完好率100%。
第四,加强配网结构的研究,制定并落实了每年各节假日、政府重要会议、各企事业单位重要活动等的紧急救援预案,确保了供电区域各种活动的正常开展。
第五、为防止三相四线制用户因零线线径篇小,三相负荷不对称而造成烧断零线,即而烧坏220V电器设备的故障,根据巡视中发现的薄弱环节、接头、接点缺陷,及时进行整改,增加重复接地、更换大规格零线,铜铝接头处严格采用过渡措施等,从精细处入手开展配网供电设备的运行维护和故障抢修工作。
第六,认真建立和完善配电设备基础台帐,98年在市公司各兄弟单位中,率先实行了利用数码相机现场拍照的一杆一卡线路台帐,在市公司专业互查和评比中,赢得了好评。
第七,积极开展QC小组和技术革新活动,20xx年的QC课题《加强配电设备管理,降损节耗》,在本公司赢得了三等奖。针对城网改造中新增的10KV柱上开关无明显断开点的特点,本人要求在开关操作前后必须每相进行验电,验明开关操作分、合正常。但验电器的绝缘手柄都比较短,且在杆上来回传递比较麻烦,本人就将验电器进行改造,与绝缘操作棒进行配合使用,人员登杆时只需将验电器的头部装在工作服的口袋里,操作后将绝缘棒倒过来装上即可,这样即增加了绝缘棒的有效长度,又确保了人身与带电体的安全距离,实践证明,使用起来很方便,即节省了操作时间,又确保了操作验电的安全。 第八,严格遵守安全生产纪律,加大配电抢修和日常维护中现场的安全工作,杜绝违章行为,积极开展创建“无违章班组”、“无违章个人”活动,把安全措施落实到了实处,近几年本人带领的配电班均被本公司评为安全生产先进集体。
二、做好城区电力设施的保护工作。
近年来,我们城区出现了因汽车碰杆、风筝挂线、人为破坏城区配电箱等而引发的停电事故,因此我们配电运行人员利用一切机会,向社会、向用户宣传电力设施保护的重要意义,配合公安部门开展打击破坏电力设施的专项整治活动,不断完善了电力设施保护的组织措施和技术防范措施,规范了各类安全标示,警示标志,特别是对施工工地附近、交通道口和居民区等处的电力杆塔、拉线、配电箱等设施采取积极保护措施,一定程度上保证了城区配电网的安全运行。
三、优质服务
本着“人民电业为人民”的服务宗旨,认真贯彻“优质、方便、规范、真诚”的供电服务方针开展了优质服务工作。优质服务工作在配网专业占了很大比重,需要好多时间用在优质服务工作上,搞好这项工作也是企业经济效益、企业形象之所在。本人带领的配电抢修班多次在县、市公司得到嘉奖,自己也获得了“XX省用户服务满意明星”、省公司“电力市场整顿和优质服务年活动”先进个人、省公司“优质服务十佳标兵”等称号。
◈ 输电线路个人工作总结 ◈
本工程为农十四师20中央投资农网完善工程35KV及以下项目(输变电施工),主要施工内容含铁件、铁塔及地脚螺栓,金具及绝缘子,户外一次设备,综合自动化系统等,此外,本工程含铁塔基础施工(基础材料水泥、钢筋等由施工方购Z)、铁塔组立、扩建35kV卡塔格孜变电气设备安装施工和土建施工等。
本工程为新建皮山农场110kV变电所至皮山农场35kV(卡塔格孜)变电所35kV送电线路工程,首端为皮山农场110kV变电所,终端为皮山农场35kV(卡塔尔孜)变电所,全线总行8.648km,单回供电,导线型号为LGJ-95/15,避雷线选用(GJ-35)1×7-7.8-1270-A-GB1200-88(非全线架设)。
本线路为新建35kv送电线路,首端为新建皮山110kv变电所35kv出线间隔西起第二间隔。
线路垂直西起第二间隔出线,终端杆距西起第二间隔25米。 皮山农场35kv变电所的现状为35kv进线间隔一回,至皮山县110kv变电所;本次扩建一回35kv间隔,为本线路使用间隔(西起第二间隔)。
送电线路总长8.648km,线路从新建皮山110kv变电所35kv间隔西起第二间隔出线,垂直门型架向西南方向行0.967km至JD1线路右转26°39′19″,此段路径消漠化比较严重(属于半流动性沙漠);线路再行5.814km至JD2线路右转39°43′27″,此段路径植被较
多(多为芦苇、铃铛刺、少量红柳);线路再行1.202km至JD3线路右转19°52′04″,此段前1km路径植被较多,后0.2km路径为耕地,线路选择跨越红枣地;再行0.665km至皮山农场35kv变电所,此段路径都在耕地里(线路选择在地埂边立杆),其中有两处要砍伐树木。本线路无跨越公路和高压线路。
本工程导线选用LGJ-95/15,地线选用(GJ-35)1×7-7.8-1270-A-GB1200-88。
导、地线防振:线路档距不超过120m时,不加装导地线防震锤。档距超过120m时,加装导地线防震锤,导线防振锤采用FR-2,地线防振锤采用FR-1。
本张路所处地段海拔1270-1290m,全线路经过地段污秽等级为III级,即大所中等污染地区,轻盐碱和炉烟污秽地区。本送电线路绝缘子选用高原型复合绝缘子;复合横担绝缘子FS-35/5.0和复合绝缘子FXBW-35/70。
本线路选用地线(GJ-35)1×7-7.8-1270-A-GB1200-88,线路在进出变电所处架设避雷线分别为1.058km和1.07km。
LGJ-95/15导线耐张线夹采用NLD-2和悬垂线夹CGU-3。(GJ-35)1×7-7.8-1270-A-GB1200-88地线悬垂线夹采用CGU-2,地线耐张线采用NE-1。其它所需金具均采用电力行业标准中的金具产品。
杆塔设计:全线路直线电杆采用ф190拔梢杆单杆,杆高12米、15米、18米,转角及耐张选ф190钢筋砼拔梢双杆打拉线,部分跨越直线杆选用ф300高18m的钢筋砼非预应力单杆,打四方拉线,立
杆困难地段采用自立式铁塔。
基础设计:钢筋砼电杆的基础用预制的钢筋砼底盘,拉线盘和卡盘,铁塔基础为现浇混凝土基础。
防腐:本工程全线路所经地段土壤不同程度含盐碱,对基础中等腐蚀,需做防腐措施。钢筋砼电杆(地面以下0.8m到地面以上0.8m)涂刷环氧煤沥青漆,并用纤维布包裹(四漆三布)。拉线棒用纤维布包裹(三漆两布)。铁塔基础由底脚螺栓处向下1.0m纤维布包裹(四漆三布)处理。
本工程开工后项目部立即按本施工组织方案,配备人员,开展前期准备工作。
根据工程承包合同、合同工期、工程设计特点及现场情况,依据本工程情况,由项目总工组织进行工程策划,技术部依据策划认真编制施工组织设计,在各分部工程和特殊工序施工前做好施工资料的编写、审核、出版、发布。
在接收项目法人提供的施工图纸后,由项目总工组织项目部有关技术人员进行图纸会审,并参加项目法人组织的施工图会审和技术交底。
针对工程特点,对施工技术的难点进行分析,并提出解决方法。 计划在本工程中采用的新技术、新材料、新工具。
为了提高职工素质,培养具有专业技术和经营管理经验的施工队伍,保障现场施工技术人员的需要,在开工前已做好技术培训工作。
开工前针对本工程设计有侧重的进行各级技术交底及施工培训。 二、施工工序总体安排 1、施工工序
电杆坑测量定位→立电杆→安装金具→架设导地线。
测量铁塔位Z→铁基础施工→立铁塔→安装金具→架设导地线。 2、工程安全、质量、工期目标及保证措施 (1)工程安全、质量、工期目标
1)安全目标:确保不发生人身死亡事故和人身重伤事故;不发生本单位责任的重大及以上电网事故;不发生重大设备安装质量事故和施工机械设备损坏事故;不发生重大火灾事故;不发生本单位负同等及以上责任的员工重伤、死亡交通事故。
2)质量目标:单元工程合格率100%;分项工程优良率≥92%;分部工程优良率90%。
严格按照施工组织设计中的安全、质量、工期目标开展各项工作,以便及时发现问题,及时采取纠正措施,确保工程的总体目标不变。
主材供应为工期关键控制点,材料必须按期供货,尽量为施工创造条件。
积极采用新技术、新方法提高施工效率,技术指导、技术监督到位,确保基础施工质量。
材料必须按期供货,便于材料及时倒运到指定地点,材料在倒运期间采取保护措施保证质量。
主要工作内容:线路交接桩;施工技术资料的编写、审核、批准;安排材料的采购;施工驻地、材料站的布Z;施工人员进行技术交底;部分机具进场;开地方协调会等。
投入全部管理人员及施工人员,运输队。
工作内容:线路复测、分坑、基坑开挖(电缆沟开挖)、道路整修、材料采购运输及检验、基础安装、基础验收等。
工作内容:电杆运输及检验、组立电杆、更换电杆、接地等。 6、架线工程
工作内容:架线施工准备包括越线架搭设、架线设备进场等工作、线材运输、人力放线及附件安装。
7、设备吊装时,因单件物品较重及为了设备和人员安全,应小心轻放,不得让设备外观有掉漆现象出现。二次母线安装时应认真核对图纸。
工作内容:进行自检、消缺、收集整理工程档案等。 三、主要工序和特殊工序的施工方法 1、复测分坑及运输施工方法见下表
在复测分坑过程中,若发现地质状况、基础型式与设计不符应立即通知设计单位或监理工程师进行协商并办理好有关手续。
材料要求:钢筋在当地采购,产品须有出厂合格证、试验报告等资料。同时还要抽样检测试验,合格后才能使用。钢筋表面应洁净、无损伤、油脂污染和铁锈等缺陷。
钢筋采用机械加工,按钢筋图准确翻样,计算并画出每根钢筋的形状和尺寸。加工时按配样表准确下料,加工成相应的形状,钢筋弯曲的部份不得有焊接接头。
钢筋绑扎完毕后,严禁踩踏,不得任意切断和移动钢筋的位Z,经过班组自检、质检员复验合格后,报监理工程师检验,并办理隐蔽工程验收手续后,才能浇筑砼。
砼配合比依据现场材料,经过试配后确定。砼的坍落度要求为3~5cm或5~7cm,砼施工前由施工员进行施工技术交底,经自检,模板支撑牢固、稳妥,标高、尺寸等符合设计要求,模板缝隙超过1.5mm时,要采取堵缝措施;模板内的杂物必须清理干净,并洒水湿润,经监理工程师验收合格,并办理隐蔽工程验收手续后,方能浇筑砼。
根据测定的砂、石含水量调整配含比中的用水量,砂、石子要严格按重量配合比称量,用水量要严格计量控制。
砼养护采用铺设一层薄膜保湿养护,养护时间应持续14个昼夜以上。砼养护十分重要,必须高度重视,认真负责地做好。
砼的质量要求:
砼所用的水泥、水、砂、石等材料,要符合设计和施工及验收规范的要求。
砼的配合比:原材料计量、搅拌、浇筑和施工缝的处理,以及砼养护,必须符合施工规范的规定。
砼捣固,必须密实、均匀,严禁出现裂缝、空洞,每处蜂窝面积应控制在规范规定的范围内。构件的尺寸、标高、边角顺直等允许偏差,应满足设计和规范标准。
浇筑砼时,必须垫好钢筋保护层,正确控制钢筋位Z,要经常检查钢筋是否变形、移位和模板是否走动、漏浆等现象,发现问题,应及时处理。
底拉盘采用平板振动器振捣,现浇基础采用插入式振动器振捣。振动棒与砼面成斜交,做到“快插慢拔”,振动棒插点“交错排列”,
插点间距不宜大于其作用半径的0.5倍,并应避免碰撞钢筋、模板、预埋件等;振动棒插入下层砼土内的深度应不小于50mm。
当用平板振动器时,其移动的间距,应保证振动器的平板能覆盖已振实部分的边缘。
浇筑柱砼时,分层浇筑、振捣,每层厚度不宜超过500mm,边下料边振捣。下料高度不宜大于2米,大于2米时,要用串筒下料,防止砼离析。
砼浇筑完后,采用自然养护,终疑后,覆盖浇水养护。养护时间不得少于14天,浇水次数以能保持砼处于湿润状态为准。养护砼的用水与拌制砼的水相同。
砼在拌制和浇筑过程中应进行如下检查,并做好记录;
检查砼拌制所用原材料的品种、规格和用量,每一工作班至少两次; 检查砼在浇筑地点的坍落度,每一工作班至少检查两次。
用于检查砼结构构件强度的试验,应在砼的浇筑地点随机取样制作试块。试块的留Z,应符合规范规定。
1)排杆前,应根据施工准备资料校对杆段型号、眼孔尺寸,并对外观进行检查,确认无误后,方可进行排杆工作。
2)按GB4623-94预应力混凝土电杆外观及尺寸检查应符合下列要求。
外表面应光洁平直。
合缝处不应漏浆。
稍端及根端不应碰伤或漏浆。
钢板圈或法兰盘与杆身结合面不应漏浆。
预留孔周围的混凝土不应损伤。
不得有环向或纵向裂缝,但网状裂纹、龟裂、水纹不在此限。内、外表面均不得露筋,内表面混凝土不应有塌落。
钢板圈焊口处内壁的混凝土端面与焊口距离不得小于l0mm。
电杆各部尺允许误差应符合规定。
3)对以上国标允许修补的电杆可用环氧树脂或其它有效方法修补,但不得用水泥砂浆修补。
4)电杆下段的下端,离心混凝土应平齐构造钢圈的底口,以解决与底盘的接触强度问题,不能用电杆的中段和上段来代替下段使用。
5)对于电杆的上段顶端封顶不全者,应补封顶。
6)排杆时先根据地形情况、立杆方法,确定排杆方向,然后平整场地,清除障碍。遇有地形不平需填土或土质松软之处,垫枕木各边1米范围应进行夯实防沉。
7)每节杆段用枕木支垫两点,从下节排起,杆根距主洞中心0.5~0.7米,支垫位Z一般距焊口0.8~1.2米左右,其杆顶的支垫位Z应避开组装横担、抱箍位Z,杆根支点要离杆根1米处,且支垫高度不能超过0.5米。
锚固。
9)注意穿钉孔的朝向,直线杆:横梁穿钉孔与线路方向一致,地线支架、吊杆、拉线抱箍穿钉孔与线路方向垂直;耐张杆的穿钉孔与线路方向一致。
10)转动杆身可用绳索进行,或用木棒下垫枕木进行撬拔,不准用钢钎穿入杆身或杆段穿钉孔内橇动。
11)如要求杆身稍微下沉,只能用铁锤打杆身下所垫枕木,不准用铁锤直接敲打水泥杆。
12)排杆时找正人员应站在杆轴线的一端,用目测或拉琴线指挥操作人员拔动杆身,使杆上、下、左、右均成一直线,同时应保证各安装孔位Z的正确,钢圈对口间隙在2~5mm,使用预拱法排杆。
13)移动杆段时应随时将杆段掩牢,使用钢钎或杠棒时,应防止滑脱伤人,撬拨杆段时应听从指挥、统一行动,拨动方向不得有人。
14)排杆时,场地高差较大需要搭架者,必须经队技师或技术员作出方案,其架应牢固可靠,同时不得下沉和晃动。
焊接方法有气焊和电焊两种,项目部没有统一规定时,施工队可任意选择一种。
气、电焊都必须由经过专业培训并考试合格的焊工担任,焊接操作时,须遵守气、电焊接的安全技术规定。
焊接前应复核排杆各孔是否正确,电杆是否正直。
应对钢圈对口及钢圈上的油漆、垢、锈等污物用砂布清除干净。
将气焊条上的油漆、垢、锈等污物清除干净,钢圈对口不平整超标时可用气割修整,严禁用焊条或其他金属填充。
焊口符合规范要求后,可先在钢圈的对称位Z点焊3~4处,点焊长度为20mm~50mm,然后对称施焊,每层的起焊点和收口点要相互错开。焊下一层时应把前一层的熔渣及飞溅物清刷干净。
焊接移动的速度应均匀,不应忽快忽慢,收口时应将溶池填满,焊缝按规定应有一定的加强面,不得有浮渣、夹渣、气孔、弧渣和咬边等缺陷。
为保证焊后杆子正直,焊接时应有人监视电杆变化,必要时调正杆身。雨雪时禁止露天施焊,焊接时杆内不得有穿堂风。
焊完后的混凝土杆弯曲不得超过杆长的2‰,否则应割断重焊。 焊完后应及时清除焊渣,自检合格后在焊口处打上焊工的钢印代号,待焊口冷却后刷一道红丹,干后再刷1~2道灰漆防锈。杆根的结构钢圈及杆顶钢圈未镀锌,也应涂沥青清漆防锈。
1)组装前必须熟悉图纸及工艺要求,特别是使用杆型型号多的工程,有很多新的材料,应与设计图纸校对。
2)组装时应注意螺栓、穿钉的穿入方向。
3)螺杆应与构件面垂直,螺头平面与构件不得有空隙。严禁螺栓以小代大,以短代长。所有螺栓不允许丝扣进入剪切面,当材料以厚代薄时,其连接螺栓应相应加长。
焊后重新打孔,并进行防锈处理。严禁用气割进行扩孔或烧孔。
5)所有杆型设计为椭圆孔的地方都应加垫片,具体情况见施工组装图。
6)直线杆的水平拉杆安装时调紧的初拉力应达到5KN以上,可用激振法和或凭经验控制。
7)所有混凝土电杆的拉、吊杆在架线前调紧达到使平面横担上翘20~30mm。
8)拉线制作:
拉线短头从线夹出口起留长300±20mm,其线头用18~20#铁丝绑扎5道,线头与主线用10~12#铁丝绑扎5~7道。
拉线与舌板应紧密接触,弯曲部分不应有明显松股,杆塔的多层拉线应在监视下对称调节,防止受力过紧或受力不均,所有电杆的拉线初拉力应调到10KN以上,可用激振法或凭经验控制,组合拉线的各根拉线受力应一致。双拉线时:上拉线装外侧;下拉线装内侧。
砼杆拉线下把一律安装防盗帽。
根据以往的施工经验和现有工机具情况,一般地形情况的混凝土电杆起吊采用倒落式扒杆进行起吊。
现场布Z:应保证牵引地描中心、扒杆顶点、制动系统中心及杆子结构中心在同一垂直面上。如受地形限制,只允许杆头偏离(杆子结构中心)不允许制动偏离。
地锚坑开挖应使受力面垂直,开挖时要求用人力开挖,以保持其原状土特性,严禁用爆破开挖。
马槽方向一定要与受力方向一致,马槽开挖一定要开到距洞底0.1米的位Z,对地夹角制动地锚马槽不大于30°,牵引地锚马槽不得大于25°。一般土质时,地锚可用角铁桩再卡木枕木后回填一部分土,起吊过程中应有人监视地锚,处于岩石或洞坑开挖困难时应用双地锚。2、放绳系统:放绳应打在1.2倍杆高以外,对地夹角不得大于45°,左、右放绳位Z应对称主杆洞,放绳的固定:埋设地锚,地形较差或有阻碍物时应设双放绳过渡。特殊地形放绳不能打在1.2倍杆高以外时,应设Z转向滑车,以保证操作者在1.2倍杆高以外操作。
吊点系统:采用二点起吊,吊点绳大小、长度也要求按措施准备。 牵引系统:整体起立时牵引系统为两套组二滑车组。两主牵引地锚相距10~15米,当采用单扳时,牵引系统只设Z一套组二滑车组。牵引绞磨应用地锚固定。应注意调整总牵引绳的长度以防“二、二”滑车组的行程不够而使杆子立不起。
扒杆系统:采用单扒杆起吊,采用单扒杆,一般扒杆放上山坡位Z,扒杆脚距离杆身0.5~1.0米,扒杆拉线可用Φ12.5钢丝绳、地锚(受力测),Φ11钢丝绳,三联桩(不受力侧)固定。固定点宜设Z杆子两侧正横线上。如在正横线上不能设Z时,可向杆顶方向偏移1~2米,不能向杆很方向偏移,拉线对地夹角宜小于30°。
应尽量收紧,起立过程中应听从指挥缓缓松出以减少震动和冲击力。整体起立时松制动要同步同速,以防由于单边受力,造成电杆弯曲过大,产生横裂。
起吊注意事项:
当各系统准备好且经检查无误后方可起吊。杆头离开地面0.8~1米左右时应停止牵引,做受力冲击试验和对地锚、角铁桩及杆身弯曲等全面检查。确认各系统无问题后方可继续起吊,起吊过程中左、右放绳随起吊速度酌情松出。
扒杆脱帽前应使杆根进入底盘,此时制动系统还不能拆除。扒杆接近脱帽时,后拦风绳应带紧且随起吊速度缓慢松出,当杆子起立约70°时,牵引速度应减慢,当起立约80°时应停止牵引,用松临时拉线方法使杆子到位。
起吊过程中四方放绳不可受力过大,当一方受力过大时应停止牵引,查明原因后方可再行起吊。
单扳时,第一根杆子可用3根拉线固定,其设Z的方向应避免对第二根杆子的起立产生阻碍,否则应在该方向上设Z双层临时拉线。用3根临时拉线时其相互间的最大水平夹角不得大于130°,临时拉线为Φ11钢丝绳。
当牵引位Z较低时,扒秆脱帽较迟,可将扒杆脚与杆坑的距离增加0.5米或将扒杆的初始角适当加大,当牵引位Z较高时,扒杆脱帽过早,此情况可将扒杆初始角减小。
修通放线道,消除放线障碍物。对于岩石露头处应垫以茅草之类的防护物,不允许导、地线与各种坚硬物直接磨擦。
对于交叉跨越物,应在跨越前做好联系工作。
本工程采用机械牵引放线,即用人力放引绳,然后用拖拉机绞磨或机动绞磨牵引采用“一牵一”方式放线,牵引绳采用∮9防扭钢丝绳,牵引力在3000N~5000N之间。并严格遵守各项规定,采取切实可行的措施防止导线磨损、打金钩,确保架线质量。
展放的线被障碍物卡住时,首先通知“停止牵引”,而后用工具和大绳处理,不得用手推拉。处理人员必须站在线弯的外侧。 在放线过程中,断股及损伤应及时按验收规范处理。
导地线线连接采用爆压连接,操作者必须持证上岗,并严格按试验报告进行操作。
耐张杆塔紧线前的准备工作:
在耐张杆塔紧线侧的反向打好临时拉线(当一侧挂线后,另一侧可不打),临时拉线对地夹角不大于45°,拉线承受张力可取最大线向张力的30%,导线临时拉线沿线路方向埋设,地线临时拉线可按
直线埋设,亦可利用边导线临时拉线。
临时拉线应打在靠近挂线点附近的节点上,并用麻皮木头或麻布包好主材角钢,以减少对钢丝绳的磨损。
临时拉线的选择:
导线每相选用10KN钢板地锚一个,埋深不小于1.0米,且应回填夯实(土质较好的地方可采用三联桩)。选用Φ9钢丝绳(或用GJ-50钢绞线),用10KN的双钩加以调节。
地线临时拉线选用Φ9的钢丝绳(或GJ-50的钢绞线),用10KN的双钩加以调节。
导线紧线张力按10KN配Z机具,地线紧线按10KN配Z机具。 绞磨牵引方向应与导线方向一致,牵引绳对地夹角不大于25°。紧线完毕后,先将导、地线保险,然后在直线杆塔上将导、地线过轮临锚,锚线角度不大于25°。
过轮临锚的工器具配备:
导线每相采用10KN钢板地锚一个,埋深1.0米。地锚洞应回填夯实。选用Φ9钢丝绳,用10KN的链条葫芦调节。
地线每根选用10KN地锚一个,埋深1.0米,地锚洞应回填夯实。选用Φ9的钢丝绳或GJ-50的钢绞线,用10KN的.双钩调节。
紧线前的注意事项:
耐张杆塔紧线前,应将拉线和临时拉线收紧,挂线前应向紧线段联的反侧预偏50~100mm,挂线杆塔要有专人看护。
各杆位应派人看护,并对本段内的导、地线进行一次全面检查,
检查是否有导线交叉及损伤等情况发生。
选择好通讯器材,确定通讯信号。
当检查各部分准备妥当、人员就位后,即可发出紧线命令。
紧线顺序:一般在紧好地线后,先紧中导线,后紧边导线;
紧线过程中,各中间杆塔要随时注意滑车活动情况,发现异常情况要立即报告现场负责人,停止牵引,进行处理。
挂线端的临时拉线要随时进行调整,保持杆塔及横担正直。
如果导、地线在紧线过程中有可能被挂住,可用绳索系在导、地线上(要用双头,确保导、地线上天后能在地面拉下绳头),在垂直线路方向将导、地线拉离障碍物,边紧线边松出绳索,以保持导、地线不被挂住。
紧线到接近弛度时,应预先发出信号,减慢牵引速度。弛度观测应从挂线端开始,依次进行,回松往返调整。
杆塔调正后,当弛度观测无误,即可划印。划印时应采用直角划印法--从挂线孔中点挂一锤球,所挂琴线与导线的交点即为划印点。
在直线杆塔上码线前,应先将绝缘子串调正。在直线杆塔上将导、地线划印后码线,码线完毕应保证所划印痕仍处于原位Z,绝缘子串垂直地面。
导线开断尺寸(即划印点向前量取的开断尺寸)必须按绝缘子串的实际组合尺寸为准。
挂线时,应尽量减少过牵引长度。
当挂好线后,检查开口销、弹簧销是否正确。一切正常后,再松出牵引绳。
在放紧线过程中,严禁有人站在导、地线的正下方及转角杆塔导、地线的内角侧。
信号人员必须清理前后半档线。
不得横跨即将离地的导地线。
紧线工具严禁以大代小。
观测弧垂的方法,可以根据观测档的现场条件和测量工具的不同选用适当的方法。为了提高测量精度,要恰当地选择观测档与观测点。
弛度观测档的选择原则:
选取连续档中的档距最大或较大者。
选取高差较小的平坦地带。
当连续档在5档及以下时,靠近中间选一档;当连续档在6~12档时,靠近两端各选一档进行观测;当连续档在12档以上时,在耐张段两端及中间各选一档(但不宜选在有耐张杆塔的档内)。
弛度观测点的选择:
为了保证观测精度,弧垂观测点即观测视线与电线的相切点应尽量设法切在弧垂最大处或附近(一般在档距中央)。当用仪器观测时,切点仰角或俯角不宜过大,以保证弧垂微小的变化亦能引起仪器读数的明显变化,亦应尽量使视线与弧垂最低点相切。
弛度观测方法与适用条件:
等长法:等长法是常用的一种简单方法,且切点在最大弧垂处。如果视线清晰,观测准确,误差较小。
异长法:异长法应用于因地形、杆塔高度限制,不宜采用等长法的档距。可以先设Z一端样板,在另一端设活动样板。
档端角度法:该方法应用范围广,但测量项目多,且需要较高的测量精度,一般应用于不能用样板法测量的档距。使用该方法时,观测角应接近高差角。用角度法时,杆塔与架空线切点不宜距离太近,以免误差过大。
弛度观测的质量要求及注意事项:
紧线弛度应在挂线后随即检查,其误差应不大于±2.5%。
导线、避雷线各相弛度允许相对误差为200mm。
架线后应测量导线对被跨越物的距离。在计入导线塑性蠕伸长并换算至最大弛度后,应满足设计规定弛度对跨越物的距离,如果发现不够,应采取措施。
附件安装一定要在杆塔完全校直、弛度调平后才能进行。
对于金具的镀锌层有局部碰伤或脱锌,应除锈后补刷防锈漆。 挂线后应及时进行附件安装,防止导线、避雷线因震动而受伤。 附件安装选用1吨的链条葫芦、双钩、拉线钳等吊装工具。在吊起导、地线脱离滑车前,应先用钢丝绳保险过渡,以防机具出问题。
绝缘子串、导线及避雷线上各种金具螺栓、穿钉及弹簧销子的穿向应统一。
开口销必须对称开口,开口角度为60°~70°,开口后不得有折断、裂纹等现象,不得用线材代用开口销。
导线不得与线夹或夹具直接接触,安装前必须在线夹表面紧密包缠铝包带,铝包带的缠绕方向应与外层线股的绞制方向一致,两端露出夹口0~10mm,且断头缠回到线夹内压住。
悬垂线夹安装后,绝缘子串应垂直,个别情况下,其在顺线路方向与垂直位Z的倾斜不超过5°,且本线路的最大偏移值不得超过200毫米。
防震锤安装:防震锤应与导地线垂直。安装尺寸:直线杆塔从悬垂线夹与导线分离点算起,耐张杆塔从耐张线夹出口处算起,其误差不大于±30毫米。
导线跳线的搭设:其弧垂应呈近似悬链状自然下垂,最小电气距离不小于1应符合设计要求。
在杆塔及导、地线上作业,必须使用双保险,安全带应系在牢固的构件上,应防止安全带从瓷瓶串下方掉出来。系安全带后必须检查扣环是否扣牢。
当工作人员登上杆塔准备出线作业时,要检查放线滑车是否处于保险位Z,其它构件是否牢靠。
感应电,则要对导、地线进行放电,以免造成人身触电事故。放电可以用绝缘铝皮线,一端搭在导、地线上,一端接地放电。
附件安装工具不得以小代大。
附件安装垂直下方不得有人。
(1)真空断路器安装和调试:
真空断路器是变电站内主要设备之一,其设备本身质量的好坏及安装的质量都将直接影响到整个电网的安全运行,为此在安装中必须特别注意施 工质量、工艺要求,加强技术管理,同时做好人身和设备的安全。
1)真空断路器的基础或支架安装必须达到以下要求:
A.基础的中心距离及高度误差不应大于 10MM;
B.预留孔或预埋铁板中心线的误差不应大于 10MM;
C.预埋螺栓中心线误差不应大于 2MM。
2)安装前应进行以下检查:
A.真空断路器零部件应齐全完好;
C.绝缘部件表面应光滑无裂缝、无剥落和缺损,绝缘应良好,绝缘拉杆连
接部位应牢固可靠。瓷套表面应光滑无裂缝、缺损,外观检查有疑问时应探伤检验;
D.瓷套与法兰的结合面粘合应牢固,法兰结合面应平整、无外伤和铸造砂 眼;
E.传动机构零件应齐全,轴承应光滑无刺,铸件无裂纹和焊接不良组装用 的螺栓、密封垫、密封脂、清洁剂和润滑脂等的规格必须符合产品技术 规定。
F.密度继电器须经过校验后再安装;
G.真空断路器的安装应在无风沙、雨雪的天气下进行,灭弧室检查组装时,空气相对湿度应符合技术要求,并采取防尘、防潮措施。
3)真空断路器的组装,必须符合以下要求:
A.应按制造厂的部件编号和规程顺序进行组装,不可混装;
B.断路器的固定应牢固可靠,支架或底座与基础的垫片不宜超过三片,其总厚度不应大于 10MM,各片间应焊接牢固;
C.密封部分的螺栓应使用力矩扳手紧固,力矩值须符合产品的技术规定。
密封槽面应清洗干净,无划伤痕迹;
D.对各个部件的调整、调节、调配要严格按说明书的要求进行; E.同相各支柱瓷套的法兰宜在同一个平面内,各支柱中心线距离误差不应大于 5MM,相间中心距离误差不应大于 5MM;
F.所有部件的安装位Z应正确,并按制造厂规定的要求保持其应有的水平或垂直;
G.已用过的密封垫圈不得使用;涂密封脂时,不得使其流入密封垫圈内侧 而与 气体接触。应按产品的技术规定更换吸附剂;
H.应按产品的技术规定选用吊装器具、吊点及吊装程序。开关安装就位后,未充气严禁作分合闸动作;
I.充气时应认真按厂家说明书操作,保证充气管内的清洁与干燥,气体的压力值应符合产品技术要求。
4)真空断路器的试验:
A.测量绝缘拉杆的绝缘电阻;
B.测量每相导电回路的电阻;
C.耐压试验;
D.断路器电容器的试验;
E.测量断路器的分、合闸时间;
F.测量断路器的分、合闸速度;
G.测量断路器主、辅触头的分、合闸同期性及配合时间;
H.测量断路器合闸电阻的投入时间及电阻值;
I.测量的分、合闸线圈绝缘电阻及之流电阻;
J.断路器操动机构的试验;
K.套管式电流互感器的试验;
L.测量断路器内气体的微量水含量;
M.密封性试验;
N.气体密度继电器、压力表和压力动作阀的校验。
(2) 隔离开关安装和调整:
1)清点所有附件,并检查附件、零件应无损伤变形和锈蚀;
2)检查隔离开关(包括接地开关)所有导电部分的接触面是否清洁,触良 好,连接前应涂以薄层电力复合脂;
查隔离开关的底座转动部分应灵活,并涂润滑脂;
4)支柱绝缘子应垂直于底座平面,且连接牢固;同一绝缘子柱的上下绝缘子中心线应在同一垂直线上,同相各绝缘子柱的中心线应在同一垂直面内;
5)隔离开关的各支柱绝缘子间应连接牢固,安装时可用厂家提供的金属垫片校正其垂直度偏差;
6)隔离开关操作机构箱的固定支架应按设计中的尺寸制作安装,并焊接牢固,操作机构箱安装位Z应正确,牢固电动操作前,应进行多次手动分合闸,机构动作应正常,平稳,无卡阻冲击等异常情况;
7)检查隔离开关(包括接地开关)动静触头表面镀银层,并用软布清擦干 净;隔离开关的闭锁装Z应动作灵活,正确可靠,带有接地刀刃和隔离开关,接地刀刃和主触头间的机械或电气闭锁应正确可靠;
8)隔离开关三相分、合闸同期值应符合厂家技术规定。
设备支架的检查。检查可以包括以下内容:检查避雷器支架的标高是否符合设计要求;检查避雷器支架的垂直度;检查避雷器支架顶面杆帽的平整度;检查设备支柱的防腐层应完好。
设备开箱与存放。打开包装箱,对照装箱清单,清点附件数量、规格应该与设计相符,随机文件、试验报告齐全。检查设备型号规格符合设计要求。检查设备瓷件外观应该清洁无裂纹、损伤,瓷套与铁
法兰间的粘合应牢固,法兰泄水孔应通畅。检查每一只避雷器的每一部分应该齐全,不得随意替代。每一只避雷器单元不得任意拆开,破坏密封和损坏元件。安装前,应Z于干燥环境中,且应分Z,不得放倒。
高压试验。用2500V的摇表测试瓷绝缘强度和底座的绝缘强度应该符合产品技术要求,测量前应将瓷套表面擦干净。测试电导或泄漏电流应符合产品技术要求。对于氧化锌避雷器,应测量有运行电压下的持续电流,以及对于工频参考电流下的工频参考电压或直流参考下的直流参考电压,测量值应符合产品技术要求。
本体吊装。先将避雷器的底座选出安装在避雷器支柱的杆帽上,固定好,注意底座与相连的避雷器本体的绝缘应良好。选出避雷器的
第一节垂直安装要底座上,用手拧好固定螺栓,注意让阀型避雷器的喷防爆板应该朝向安全地点,不得朝向其他设备,以免避雷器动作时引起其他设备短路。依次选出避雷器的中间各节按照次序依次安装在下节上,注意每一节的方向应该与第一节相同。
安装在线监测仪。开箱检查在线监测仪,查看额定电压、型号是否与避雷器配套,与设计相符。对照装箱清单清点所带附件。检查外壳有无破损,动作是否可靠。只有证明动作确实可靠后方可安装使用。安装时,应轻拿轻放,以免损坏玻璃罩。
选用一25×4的铜排或Ф6mm的铜棒,根据避雷器的位Z制作成美观的形状,将避雷器本体与在线监测仪的端子相连,要求连线形状
基本统一,并列安装的避雷器在线监测仪高度一致,在线监测仪的位Z安放在利于运行侧,便于运行人员巡视设备时检查。所有避雷器在线监测仪的起始数据应该相同。
将避雷器的设备支架按照设计要求用扁铁与主接地网相连,对于设计有接地极的,接地极按照要求布Z,埋设深度要不小于1.7m,接地极之间的连接带要有不同的2点与主接地网并连,质量符合规范接地的要求。
避雷器在线监测仪的接地端要与主接地网相连,接地线规格符合设计要求。
避雷器必须有铭牌。
上下节编号必须一致。
避雷器底座螺栓必须有双平垫、单弹垫。
避雷器底座螺栓扭矩为60N〃m.
避雷器三相必须在一条轴线上.
避雷器无锈蚀、无污染。
-
工作计划之家(fz76.COm)不火但超值系列:
- 输电线路个人工作总结 | 配电线路个人工作总结 | 配电线路架设个人工作总结 | 配电线路专业个人工作总结 | 输电线路个人工作总结 | 输电线路个人工作总结
如底座不平须加垫片时不得超过3片。
如加垫片必须穿过螺栓。
放电计数器成45°俯角安装,接引小母线应刷黑漆。
相位漆刷在设备帽上为直径100的圆形。
接地扁铁紧贴杆柱,并刷黑漆,黑漆不得刷到设备支柱上。
互感器是电力系统中供输电线路施工组织设计测量和保护一次系统和二次系统的联络及反映电气设备正常运行和故障情况等不可缺少的重要设备.
设备支架复验.首先用经纬仪测量其纵、横轴与定位轴位轴线位移应在0~5mm之内,垂直度偏差小于L/1000且不大于15mm。核实支架接地件应符合设计要求。测量互感器支架相间的距离,误差为±5mm。测量互感器支架的垂直高度,误差应在0~10mm之内,且同一组互感器支架测量的高度数据基本一致;测量支架柱顶板的水平度应在0~3mm范围之内。
设备开箱。根据施工图纸及装箱单将互感器搬到运到位,Z放位Z地基密实,搬运过程中轻吊轻放,开箱过程中,注意别损伤箱内部件。设备开箱后,核对箱内部件、备件、专用工具的数量、同装箱单相符,型号与设计型号相符。
检查镀锌部件应无镀锌层脱落、无锈蚀、无变形;瓷件的颜色一致,无破损、无裂纹、无弯曲;胶合部件密实牢固。检查铭牌、接线图标志、型号规格等是否符合设计要求,检查二次接线端子标志是否清晰。检查二次电缆接线盒内部有无渗油,二次接线头有无脱落。检查互感器的油箱、取油阀、油标及上部胶合处有无渗油、油箱及上帽有无变形;一次接线板有无氧化、凹凸不平等现象。具有膨胀器的互感器应检查油位是否正常,油位计玻璃管中应充满变压器油,油位指
示线应正常。
根据开箱情况,认真填写开箱记录,参加开箱的各级负责人签字。 2)设备安装
高压实验。一般在安装前可以做以下试验:测量绕组的绝缘电阻;测量互感器一次绕组及套管的介损值;测试互感器二次绕组的电流―电压特性;测试互感的变比是否符合设计要求;检查互感器三相接线组别的极性;测试前几天浸式互感器的绝缘油的微水、色谱、绝缘强度符合规范或说明书的要求。
设备吊装。指挥汽车吊缓缓地起吊,当互感器上部离开地面200m时,复检吊索及尼龙绳的情况,若无异常继续起吊。互感器立直后,指挥塔吊稍微松绳,将4根吊索Z入相应的安装挡板槽内,检查绑扎绳是否有松动。指挥塔吊缓缓地将互感器吊至支架柱顶板上,穿上底座螺栓紧固。用水平仪测量互感器的纵、横轴线,保证同设备支架在同一垂直轴线,测量气体的微水含量在合格范围内,接线盒面向巡检侧。根据图纸设计的互感器变比的要求,更改一次绕组的串并联方式。
设备吊装注意事项。所有紧固件的穿向,若厂家有规定的,严格按照说明书进行安装,否则应遵循以下原则:
用水平仪测量互感器的纵、横轴线,保保证同设备支架在同一垂直轴线。
对全体人员进行技术交底,交底记录要记好、保存,参加人员每人都要签字。
充油互感器的油位调整:
安装完成后,检查油位指示线是否正常。如油位偏低,应添加合格的应压器油(耐压强度及各种指标满足运行要求)。
加装油时,将储油柜内剩余的油和凝聚在储油柜底部的水分由储油柜下部的放水塞放出。注油时应防止水分、灰尘及其他污物进入互感器内,注完油后将油塞装好。
接地。设备安装完成后进行设备接地。接地时应注意以下事项:互感器的本体应该可靠接地;互感器的末屏应该与外壳可靠连接;互感器的端子箱应该可靠接地;凡与主接地网相连的接地用材料应符合设计要求,质量应符合规范要求。
1)安装前对各部件外观进行详细检查,绝缘子应固定牢固,瓷件无破损。
2)相间距离误差应不大于10 mm,相间连杆应在同一水平线上。安装结束,实测相间距离误差为5 mm,不水平度为2 mm。
3)支柱绝缘子应安装牢固,三相V型夹角应一致,同一侧瓷柱应在一条线上。
4)主触头、三相触头接触应同期,相位差应小于5 mm,安装结束现场实测为3 mm。
束用0105 mm ×10 mm塞尺塞不进去,转动部分灵活,固定牢固。
施工机具配备原则:提高施工生产效率,保证按照合同工期完成施工任务,保证施工质量。我项目部对机械设备及工器具进行全面投入,做到装备精良,合理安排,在每道工序施工前,机具均由项目部统一调配,并且保证用于现场的工器具合格且状态良好,保持机具的完好率和外观清洁,充分发挥其机械效率。
劳动力的筹集将择优选用技术素质高、思想觉悟好、操作熟练、责任心强、吃苦耐劳并长期在我公司工作的劳务队。
在该工程的劳动力使用上,我们将按专业工程编排各专业队组,不打乱工种界限,并根据工程的综合进度,安排两班作业。
由本公司专业施工队上岗作业,以保证各分部分项工程的产品质量。在劳动力组织上严格按分段要求,按时间和工序进入,保证每个分部分项工程及专业班组能够连续施工和均衡生产,达到流水作业施工的目的。
严格按照劳动合同法与所有工人签定劳务合同,劳务合同经劳动部门认可方有效。
建立用工档案,包括工人的姓名、性别、籍贯、身份证复印件,并报监理备案。
建立工资发放登记制度,保证每月的进度款中的人工工资部分足额发放到农民工手中,发放的工资均登记成册,并由员工本人签字生效。登记成册的工资单报监理及建设单位各一份。切实保护女工权益,严禁使用童工,依法保障农民工职业安全卫生权益。
建立工人维权举报、监督制度,并公开举报电话,公司安排专人及时进行相应事务的联系和处理。
形成全面维护农民工合法权益的氛围。除了建立诚信制度、民工工资支付情况的监控制度,建立企业付薪保障、欠薪预警、欠薪责任假定制度外,还要依照劳动合同法和国务院有关规定,按照“谁用工谁负责、谁立法谁负责”的要求,层层分解任务,逐一落实责任。
遵守有关法规要求,不搞层层转包,使工人与本企业关系明了,便于处理问题。
搞好工人就业服务和职业技能培训。
按照施工进度、部位和工程的施工网络计划要求陆续进场。在总进度计划中主要考虑电杆组立、导线架设及设备安装上,因此在前期主要的建材都集中在电杆、导线等。在实际施工过程中也可根据现场具体情况进行调整。原材料的使用,宜提前进行调查和采购,以确保在约定工期内顺利完工。
针对本工程,我们将按照项目法施工的原则,组建本工程项目部,配Z管理经验丰富、作风顽强、专业技术全面的项目领导班子和专业技术人员,对该工程实施项目管理,严格按照本工程招标文件中各项条款所规定的工程内容、工作范围、权利、义务和职责,管理好本工程的施工工作,按照承诺实现工程的工期目标和质量目标。项目部组织一个高效、精干、强有力的施工队伍,配备完整的管理人员及有经验的、素质稳定的施工班组,按基础、主体结构、装饰装修等不同阶段,分别考虑和安排。为保证施工质量,提高效率,便于核算,各作业班组保持相对稳定,并由项目部统一安排,统筹高度。
工程项目部人员构成:项目经理1人;项目副经理1人,项目技术负责人1人;专职质检员1人;专职安全员1人;施工技术员2人;试验员1人;材料员2人;保管员2人;预、核算员1人;机械管理员2人;资料员1人。
进场准备、测量定位:208月1日至8月16日 基础施工:8月17日至8月24日 立杆及金具安装:8月15日至9月14日。 架线施工:9月15日至10月13日。 变电站扩建部分:9月5日至10月11日。 具体进度计划见施工进度横道图。 二、工期保证措施
施,保证工程按期保质交付使用。
项目经理对各专业施工队实行工期、质量、效益安全承包,贯彻实行先验后计价,优质优价原则,拉大优良品与合格品之间的价差,充分调动发挥全体员工的主动性和积极性,实行全方位的控制,确保施工承包的全面完成。
科学安排工程进度计划,对工程施工全过程实行动态控制,对线路上的人、财、物、设备加强管理和调配。
制定工期控制点,严格按控制点要点控制工期,如因特殊原因控制点有延误,后续控制点必须采取补救措施,不得顺延。
积极准备资金,作好外购材料的采购供应,保证外购材料设备按计划进场,杜绝因材料、设备供应不及时而造成的窝工现象。
作好雨天准备,保证施工不受影响,保持排水畅通,小雨不停工,除人不可抗拒因素外,总工期将不受影响。
在施工进度计划贯彻执行时,首先检查是否协调一致,计划目标是否层层分解,互相衔接,组成一个计划实施的保证体系,以施工任务书的方式将作业下达到施工班组,明确具体施工任务、技术措施、质量要求等内容,使施工班组须保证按作业计划时间完成规定的任务。
为实施施工进度计划,将规定的任务结合现场施工条件,编制月、旬、周的作业计划,使施工计划更具体、更切实可行。
在月、旬、周计划中要明确本月、旬、周完成的任务及所需要的各种资源量,坚持日平衡、旬调度,确保月计划的实施,以保证该工
程总工期的实现。
在计划任务完成的过程中,各级施工进度计划的执行者都要跟踪做好施工记录。
加强对各种施工机具的维修、保养,制定保养制度,机械站每周查一次,保证生产顺利进行。
资金是保证施工进度的关键,在资金上对工程设银行专户,专款专用,保证工程的实际需要。
加强施工进度计划检查和落实及调度工作。
确保工程进度,在工程项目施工过程中必须经常或不定期地跟踪检查施工实际进度情况,及时收集施工进度信息,整理统计检查数据,比较实际进度和计划进度,对检查的结果作出及时处理。
为保证总目标计划的实现,在计划实施过程中必须坚持十二字方针:“日保旬、旬保月、月保季、季保年”。及时编制月、旬计划,实施过程管理,同时应做好施工记录及施工进度统计表,为施工进度分析和调查提供信息。
做好施工项目计划,实施调度制。
施工中的调度是组织施工各阶段、环节、专业和工种相互配合、进度协调的指挥核心,也是施工进度计划顺利实施的重要手段,掌握计划实施情况,协调各方面关系,采取措施排除各种矛盾,加强薄弱环节,实现动态管理,保证完成作业计划和实现总进度目标。
采用调度会议或生产碰头会形式,汇报生产执行情况和存在的问题。由项目负责人主持共同研究分析计划提前或拖后的主要原因,及
时调整人、财、物各种资源的平衡,采取相应的防范和保证措施,调节各薄弱环节,最后做出调度决策并贯彻执行。
基础施工、组塔、架线开工前,做好所有的前期准备工作,合理安排、组织人力资源,保证施工连续性,做到不窝工,以保障工程的顺利进行。
采用经过检验合格的经纬仪进行线路复测,提高施工工效。 基础开挖当有施工机械进场条件时,采用机械挖掘提高施工效率。
依据招标文件、施工图、有关规范编制各工序的《施工技术手册》及《施工方案》,从技术上保证工程的顺利进行。做到奖罚分明,从管理上保证安全、质量、进度及文明施工,并最大程度上的提高工程进度。
基础、杆塔施工单个施工队应分成两组,做到流水作业;架线全过程流水作业,合理选择放线场地,各队密切配合、环环相扣,做到不窝工。
为减少被跨越线路办理停电的时间,尽可能提前考虑停电的施工方法和措施,以保证施工按计划进行。
按甲方的要求,配合监理工程师代表对施工进度全过程控制,所有的工序做到一次验收合格,避免因返工而造成对工期的影响。根据招标文件进行本工程工程的安全、质量、文明施工工作。
各道工序的施工,严格按照投产达标的质量要求执行,责任到人,一次到位,认真负责。减少返工,降低工程成本,提高劳动生产率。
坚持文明施工,尊重当地民俗、民风、民族风情。
◈ 输电线路个人工作总结 ◈
为贯彻落实国家电网公司、江西省电力公司2014年安全生产工作意见及关于做好2014年电网春检工作的要求,强化现场安全管理,落实安全规章制度,切实做好春季安全大检查工作,及时发现、消除安全隐患,夯实安全生产基础,保障电网的安全运行和可靠供电。近日,铜鼓县供电公司推出多项措施开展“春检”工作。
春季是雷雨多发季节,电网设备经过冬季干燥、寒冷及高峰负荷的煎熬之后,部分设备防雷、防雨水冲刷和耐受腐蚀的能力大大减弱,为此,该公司全力推出多项措施开展春检工作。成立以经理为组长的春检领导组,明确春检安全工作目标,对领导组成员的职责进行分工,做到责任落实到人,保障春检工作的有序进行;做好输电线路及变配电设备的防雷检查,测试各线路防雷装置及变电站接地网电阻,对达不到阻值要求的立即整改完善,对受雷电危害频繁的电网设备,按电力防雷技术标准和要求,增设防雷设备;做好线路电杆、铁塔基础的巡视检查,防止雨季滑波、拉线锈蚀、松动造成倒杆事故;检查各变电站电缆沟、下水道的通畅情况,预防洪涝灾害事故;加强配电变压器低压漏电保护装置及用户漏电保护器的检查,做好预防试验,确保漏电保护器动作准确而快速;开展继电保护装置和自动化设备的检查,根据省公司继电保护整定原则和要求,强化继电保护定值的核算和整定,防止保护拒动和误动;加强安全教育培训,组织全员干部员进行安全教育及“安规”学习;做好各生产单位的绝缘棒、验电器、绝缘鞋、绝缘手套等安全工器具的外观检查和周期性试验,杜绝不合格的、达不到安全生产标准要求的设备进入工作现场,确保作业人员的安全。
我们有决心在分公司在正确领导下,在经理为核心的领导班子带领下,积极创造良好的`安全生产新局面,把全年的安全生产工作抓好,全面完成我局的安全生产指标。
◈ 输电线路个人工作总结 ◈
作为大四的准毕业生,根据学校的教学要求,我们输电专业的学生终于迎来了毕业实习。经过这差不多十多天的实习,我感觉自己在输电专业知识学习上有了很大的补充与提高,这次生产实习,是培养我们实际动手能力和分析问题、解决问题能力,学会自主查阅资料,理论与实践相结合的学习;这次的实习是锻炼我们从事专业技术工作以及治理工作所必须的各种基础技能和实践动手能力并培养了我们理论联系实际、从实际出发分析问题、研究问题和解决问题的能力,将所学知识系统化实际化;培养我们热爱劳动、不怕苦不怕累的工作作风。同时也是毕业设计选题以及设计工作原始资料的来源,为我们广大毕业生在即将踏上工作岗位打下扎实基础。现将我这段时间的实习作一个总结。
通过为期十天左右的实习,我收获了良多,虽然实习期不长,但是内容却是丰富的,第一天我们举行了实习动员大会,由于我们在学校所学的都是理论知识,对输电线路的设计,施工,运行,维护等工作的实习操作都不熟悉,所以进行现场的实习对于我们来说是十分重要的,也是一个难得的磨练我们自己的机会。在实习大会上老师给我们讲了一些实习过程中的要求,要我们明确实习的目的,端正学习态度和谦虚好学的学习精神,要学到真正的知识不能空手而归,我们都怀着激动的心情,对这次实习充满了期待。后面我李老师带领我们大家参观了猇亭培训基地参观了铁塔以及看员工登塔。
◈ 输电线路个人工作总结 ◈
在我们平凡的日常里,我们都可能会用到承诺书,承诺书如经合同认可,可以作为合同的一部分一同履行。还是对承诺书一筹莫展吗?下面是小编为大家收集的`输电线路工程质量承诺书,仅供参考,大家一起来看看吧。
隆务-泽库110kV输电线路工程,将严格遵守《建设工程质量管理条例》、《建设工程安全生产管理条例》、《110kV~500kV架空送电线路施工级验收规范》、《国家电网工程建设达标投产管理规定》,自觉履行各项应尽义务,为体现本人和本企业遵章守法的决心,现特向青海火电工程公司送变电分公司郑重做出如下承诺:
1、严格执行公司C版质量体系文件。科学管理、持续提高产品质量,以满意的服务、满足顾客需求。
2、110kV隆务-泽库输电线路工程,实现工程达标投产,确保工艺质量、提供优质高效服务,争创省公司“输变电工程安全文明施工标准化示范工程”;
3、施工项目检验率70%,检验准确率大于95%,数据记录达到98%,工程验收合格率达到100%,隐蔽工程检验内容完整,签证手续齐全;
4、送变电工程项目一次验收合格率在90%以上;分项工程优良率大于85%,单位工程优良率大于85%;顾客满意度大于85分;
5、技术资料软件质量符合有关规定,做到资料与工程进度同步;
6、严格执行材料进货检验制度,杜绝不合格产品进入施工现场;
7、严格按照公司规定使用机械设备,并定期进行维护保养;
8、严格执行工程质量三级验收制度,上道工序不合格严禁进入下道工序;
9、加强对分包单位的管理;
10、其他违反法律、法规的行为。
11、愿意接受分公司各级领导、业主监理及其他专业公司的监督。从服务质量、工程质量、工期进度,从管理、技术到作业施工入手严格把好质量关。为企业树立良好形象。
此保证书一式二份、送变电分公司及本人各执一份。
送电分公司
项目经理: 承诺人:
年 月 日
◈ 输电线路个人工作总结 ◈
我叫刘x,xx年12月入伍,辽宁省XX市人。现任xx连队外线2班线路维护员。2年的部队生活即将告一段落,回顾这2年来的工作本人在各级首长精心领导下,无论是在新兵下连后警卫排的一年还是来到xx连队,都受到了各级领导的充分认可,两年来,无论是在工作学习还是在训练中都能够积极主动。各方面都取得了很大进步。下面,我就将这两年来的思想、学习、生活、训练等方面情况作以下述职:
平时努力学习政治理论,始终做到政治上合格,认真学习贯彻落实科学发展观,并及时完成上级规定的理论学习计划通过学习提高自己分析事物,解决问题的能力。
自从警卫排下连以后,面对新的工作,新的专业。什么都不懂感觉很陌生,首先,我从思想上认识学习的重要性。积极参加连队里面的各种学习,课中认真听讲并做好笔记,课后认真学习有关理论知识,深刻探讨,使自己的知识有了进一步提高。
三、生活方面
严格遵守上级的`有关规章制度,平时没事不外出,有事外出按级请假,按时归队销假,外出自觉维护军人良好形象,没有夜不归营现象,能坚持好一日生活制度严格要求自己,时刻用条令条例约束自己。
1 政治理论学习的不够深,只能学习一些常见知识和表面知识,各种笔记记的不是很全。
2 军事训练不能始终保持良好的作用,专业学习不够深,队列素质不强。
3 作风纪律有时放松,不能一如既往的保持,在细小方面重视程度还不够。
在以后工作中,对学习加大力度,深刻了解,认真思考,端正思想态度,把训练的每个科目坚持做好。在平时的生活中严格要求自己,把安全工作重视起来。坚持安全第一,预防为主的方针,对工作提高标准水平,圆满完成各项工作任务,为以后打下良好基础。
以上是我的述职报告,在以后的工作中,我将以更高的标准来要求自己,争取把各项工作完成得更加圆满。
◈ 输电线路个人工作总结 ◈
一、杆塔巡视:
1、杆塔是否倾斜:铁塔构件有无弯曲、变形、锈蚀,螺栓有无松动,混凝土杆有无裂纹、酥松、钢筋外漏,焊接处有无开裂、锈蚀;木杆有无腐朽、烧焦、开裂、绑桩有无松动、木楔是否变形或脱出;
2、基础有无损坏、下沉或上拔,周围土壤有无挖掘或沉陷,寒冷地区有无冻鼓现象;
3、杆塔标志(杆号、相位指示牌)是否清晰、完好、明显,保护设施是否完好;
4、杆塔周围是否有水淹、火灾、地基土质是否松散;
5、杆塔周围是否有鸟巢、风筝、塑料薄膜、蔓藤等杂物或其他堆砌物。
二、横担及金属巡视:
1、木横担有无腐朽、烧损、开裂、变形;
2、铁横担有无锈蚀、歪斜、变形;
3、金具有无锈蚀,螺栓是否紧固、有无缺帽,开口肖有无锈蚀、断裂、脱落。
三、绝缘子巡视:
1、瓷件有无脏污、损伤、裂纹及闪络痕迹;
2、铁脚、铁帽有无锈蚀、松动、弯曲;
四、导线(包括架空地线及耦合地线):
1、有无断股、损伤、烧伤痕迹、在化工、沿海或其他有腐蚀性气体的区域有无腐蚀现象;
2、三相驰度是否平衡,有无过紧过松的现象;
3、接头是否良好,有无过热现象(如接头变色、雪先融化等),连接线夹弹簧垫是否齐全,螺帽是否紧固;
4、过(跳)引线有无损伤、断股、歪扭、与塔杆、构件及其他引线间的`距离是否符合规定;
5、导线上有无抛扔物、风筝等,固定导线用绝缘子上的绑线有无松弛或开断现象;
五、防雷设施巡视:
1、避雷器瓷套有无裂纹、损伤及闪络痕迹,表面是否脏污、避雷器固定是否牢固;
2、引线连接是否良好,与临相或塔杆距离是否符合规定;
3、各部附件是否腐蚀、,接地端焊接处有无开裂、脱落;
4、保护间隙有无烧损、锈蚀或被外物短接,间隙距离是否有异常;
六、接地装置巡视:
1、接地引线有无断股、丢失、损伤,保护管有无破损、丢失、是否牢固可靠;
2、接头接触是否良好,线夹螺栓有无松动、锈蚀;
3、接地体有无外漏,严重腐蚀,在埋设范围内有无土方工程。
七、拉线、顶(撑)杆、拉线柱巡视:
1、拉线有无锈蚀、松弛、断股及张力分布不均现象;
2、水平拉线对地距离是否符合要求;拉线绝缘子是否损坏或缺少,拉线是否妨碍交通或被外力损坏,拉线棒、抱箍等金具有无变形、锈蚀,拉线固定是否牢固,拉线基础周围土壤有无鼓起、塌陷、缺土现象。
八、通道巡视:
1、通道有无易燃、易爆及腐蚀性气、液体,有无杂物堆积;
2、周围有无易漂浮物(塑料薄膜、杂物等),及天线、烟囱、违建等有碍线路安全的物品;
3、有无威胁线路安全的施工、爆破、取土、放风筝、射击、飘洒金属、在拉线及塔杆上栓牲畜等行为及工程机械、脚手架等物品;
4、注意通道内的树木、竹林等的生长情况,确保植物与线路的安全距离;
5、注意通道内有无山洪、泥石流、积水、火灾等灾害现象;
九、柱上变压器巡视:
1、外表是否干净、铭牌完好、清晰、有无漏油、冒烟、喷油、腐蚀现象,变压器运行无异响;
2、套管是否清洁,有无裂纹、损伤、放电痕迹;
3、分接开关指示状态正常,换接良好,各电气连接点无锈蚀、闪络、烧损现象;
十、柱上油断路器和负荷开关巡视:
1、外观无渗、漏油、锈蚀现象,油位正常;
2、套管有无破损、裂纹、严重脏污及闪络放电痕迹;
3、开关分、合位置指示是否清晰正确,开关固定是否良好,引线接点及接地是否良好,线间及对地距离是否正常;
十一、环网柜巡视:
1、围栏无受损,箱体外观应无损伤、锈蚀或严重变形、箱体基础牢固无破损、裂纹,安全警示标志及运行标识齐全、清晰,箱门锁具齐全、箱门开关灵活;
2、电缆井盖完好齐全、电缆孔洞封堵严密,箱体内部与电缆井之间封堵完善,电缆底板安装完全,电缆井内无积水、箱内无受潮或临时进水现象,电缆间隔、出线标志齐全,与贴在箱门内的一次接线图一致;
3、防护区内无施工、挖掘现象,无腐蚀性物品堆积,箱内整洁、无杂品堆放(包括电缆T型头等备品);
4、开关分合闸指示灯、带电指示灯、故障指示装置运行完好、电压切换及电压表指示正确,气体压力表显示正确,操作手柄完好;
5、环网柜运行无异音接地开关打开(处于分闸位置)时,接线间隔应闭锁;
十二、分支箱巡视:
1、围栏无受损,箱体外观应无损伤、锈蚀或严重变形、箱体基础牢固无破损、裂纹,安全警示标志及运行标识齐全、清晰,箱体接地良好,箱门锁具齐全、箱门开关灵活;
2、电缆井盖完好齐全、电缆孔洞封堵严密,箱体内部与电缆井之间封堵完善,电缆底板安装完全,电缆井内无积水、箱内无受潮或临时进水现象,电缆间隔、出线标志齐全,与贴在箱门内的一次接线图一致;
3、防护区内无施工、挖掘现象,无腐蚀性物品堆积,箱内整洁、无杂品堆放(包括电缆T型头等备品);
4、各电缆插接头插接应到位,备用电缆出线套管应有绝缘防护帽,防止电缆头受潮;
5、运行无异响。
◈ 输电线路个人工作总结 ◈
一、个人工作介绍
我从19xx年进入桂洲供电公司华口电站工作,到20xx年在容桂供电所运维三班工作已经xx年了,在这xx年来,我主要从事配电线路运行、维护检修、故障抢修等工作。在上级领导的关怀下,周边同事的帮助下,我很快适应了岗位工作,能熟练掌握相应的专业知识和技能。也许,许多人都认为配电线路维修工作不过是公司里一项普通的工作,但我在工作中却获得的不一样的感受,运维班工作不仅仅只是一项简单的体力劳动,更不是日复一日的机械重复,它还需要投入大量的脑力与精力。随着科技的日新月异,配电设备的与时俱进不断翻新,新产品、新技术层出不穷,我在感受到电力事业发展的同时,也深知自己需要通过不断的努力自学,增进自身知识才干,才能更加胜任今后的工作。工作中有苦有累,但同时也充实而快乐,客户的认可、同事的赞扬、领导的肯定都能成为我今后更加奋发进取的动力,而这xx年时间的实践和学习无疑也将成为我人生中重要的精神财富,指导我今后的道路,完善我未来的人生。
二、个人工作总结
(一)工作感想
一是运维配电线路时需要注意质量与安全并行。在xx年的具体实践工作中,我不仅掌握了运维配电线路的具体操作流程,还深知工作过程中安全因素始终是最重要的注意事项,了解了可能会引发安全事故的一系列因素。虽然,当前运维配电线路安全事故逐年减少,但还是存在许多人为疏忽的安全隐患,一个不小心就会发生安全事故,所以,我时刻提醒自己要注意日常工作中的安全问题,不要马虎大意,更不要抱着无所谓的态度开展工作,耐心、细心才能避免不必要的事故发生,在确保工作顺利完成的同时,保证自己的人身安全,不仅是对自己负责,更是对公司负责的一种表现。同时,对新来的同事,我更是不厌其烦的向他们传授具体的操作规范,只有规规矩矩的完成运维各项程序,达到公司和客户的具体要求,才能最终保证工作质量和安全并行。
二是在工作中学习,在学习中培养自身能力的增强。在每天的具体工作中我都能学会许多东西,通过自身学习的积累,掌握和管理好配电网络新设备,从而获得更多的新知识、新技术。在这些年的学习实践中,我对新型变压器、柱上开关、电缆分支箱、环网柜等有了一套比较成熟的管理和运行经验,对供电事故的分析和判断相对比较果断、准确,有效地减少了事故处理的时间,这些能力的获得既然单位领导认可,也能获得同事赞誉,同时还激励我勇于创新、锐意进取。
在学习中培养自身能力的增强有许多例子,比如说在针对10kV配电线路陈旧、设备老化、故障常出的这一现象,我就充分发挥了多年的经验优势,积极工作、大胆探索、实践,制定了一系列的改造方案,如线路防小动物、抗雷害、接地装置等的技术改造项目,得到明显的效果,为线路设备的健康运行提供了保障;再比如,我在参与110kV容奇站和华容站的10kV开关柜设备安装及所有10kV电缆终端头、电缆中驳的制作中,十多年来设备一直得到安全运行,从没有发生一起设备事故;另外,我参与本所的户外配电变压器典设的安装改良工作,有效减小施工费用和缩短安装时间;针对原有的10kV接地线组连接端子部位容易松摆问题,我对接地线进行改装解决存在问题,在检查工作中得到专家好评并采纳等等,这些都是我通过具体实践和大量学习的基础上,获得的能力提升。
三是对运维工作有了全新的理解。过去,我曾经也以为运维工作是一项简单而轻松的工作,事实上它们看似简单,其实要干好还真不容易。现在虽然运维工作可以借助精密仪器从而省力很多,配线维护工作也不向过去那么繁琐难懂,但具体的运维流程还是要在规定的时间内完成,无论是刮风下雨、酷暑严寒都需要我们兢兢业业的完成运维工作,有时候遇到客户不在家,你就要一趟一趟的跑直至完成任务;有时候碰上小区客户,你就得一层一层的上下楼梯进行业务;遇到难缠的客户,你就得一遍又一遍的进行细心、耐心的讲解。印象最深的,莫过于近三年的配网十二五规划工作,这项工作必须根据地区供用电特点,这就需要在广泛调查和深入学习的基础上提出多种实施方案细则,投入的精力和时间是常人难以想象的,但当我为基建部提供配电供电网络设想图,为配网线路改造的合理性、经济性提供了依据时,我发现一切的努力都是值得的,电网运行质量全优就是对我自己的最好回报。
四是严谨做事,认真做人。我在工作和生活中,始终坚持严谨做事、认真做人的宗旨。工作上,始终认真的做好所属管辖区内的配电线路设备的日常维护和检修工作;对管辖区内的配电设备台帐资料进行核对工作;对所属理辖区内的所有配变进行周期性检查;进行负荷测量工作,针对有超载、满载的配变进行严密的监察;完成了多个大修技改项目,并制定多项的技术改造项目上报工作。生活上,始终以运维班的每个同事为老师、为伙伴、为家人,能够谦虚地向周围理论水平高、业务能力强的同志学习,取人之长,补己之短,努力丰富自己、充实自己、提高自己。并且不安于现状,始终在突破自己,通过专业培训等努力学习配电专业知识,掌握了技师应知的基础理论,在工作中学以致用,积累操作经验和处理能力。
(二)工作中存在的不足
xx年的具体工作和实践学习,专业能力技术虽然不断增强,但在一些具体而微的细节处,我还是有存在不足的地方,表现如下:
一是具体的操作技能和专业知识仍需要进一步更新。运维工作是一项日新月新的工作,容不得一丝的懈怠,需要长期的坚持更新知识储备和技能获得。在这方面,我虽然投入的大量的时间和精力进行学习深造,但还是未能达到自己理想的状态,甚至有时候产生偷懒的心态,觉得学好学坏一个样,这种思想的滋生是非常不利于自己进步的,必须坚决杜绝自我焦躁的情绪产生,坚持不断学习专业知识,钻研新的技术,总结摸索实践技巧和技能,进一步增强自身独立思考和解决问题的能力。
二是工作方法需要改善。对新来的同事,在传授技能时有时显得不够耐心细致,不能够很好的鼓励后进、培育新才,这需要引起自身的重视,杜绝骄傲自满的不良情绪,工作上还是要讲求团队合作,和谐共赢。
在接下来的工作中我将对自己的缺点进行改正,弥补自身的不足,争取以更好的工作状态出色的完成公司交代的任务,让自己更加完善、更加成熟,从而达到公司要求,回报公司培育。
三、今后的努力方向
回顾近xx年来的工作,对照自己的职责要求,我决心在今后的工作中认真把握好以下几个方面:
一是努力自造,进一步增强自身技术能力
在今后的工作中,我要更加注重学习的重要性和自觉性,努力学习政治理论丰富自身政治素养;努力学习业务知识丰富自身及专业素养。学到老活到老,牢固树立终身学习的观念,通过学习来不断提高自身的综合素质。
二是做好工作,进一步强化自身岗位本领
做好自己的实际工作,在工作中始终树立忠于职守、爱岗敬业、开拓进取、乐于奉献的职业道德。培养自己敢于负责有担当和勇于克服一切困难的精神,在具体实践里懂得发现自身的不足和缺点,加以创新和改进。同时,坚持服务优先,以人为本的工作宗旨,在自己负责的各项工作中,力争把工作做全面、做到位,认真履行工作的各项义务。
三是不断创新,进一步夯实工作实在性
随着运维事业的不断发展,新情况、新问题会越来越多,工作任务也会越来越重。要学会积极适应形势的发展需要,对过去的工作进行认真细致的总结、分析、巩固、和升华。要求自己,始终以良好的精神状态、饱满的工作热情、全新的思想意识应对全新的工作。不断创新工作方法、工作技能的同时,还要求自己坚持说实话、办实事、求实效。
四是严于自律,进一步提高对自我的要求
严于律己宽于待人,不论工作还是生活,都要以此为标准要求自己,完善自己。工作上认真负责,时时处处坚持用公司的各项规定严格要求自己,使自己的言行符合时代要求,树立积极的人生观、崇高的精神境界和道德情操。
-
推荐阅读:
输电线路个人工作总结(系列十八篇)
配电线路维修员工个人工作回顾如何写
学生个人工作总结(推荐十四篇)
国土个人工作总结(精华十四篇)
[推荐]电工个人工作总结
财务个人工作总结及计划(十四篇)
-
想了解更多【输电线路个人工作总结】网的资讯,请访问:输电线路个人工作总结
本文来源://www.fz76.com/gongzuozongjie/125795.html